The annual sewer main flushing program in Rothesay begins on Monday, Oct. 17,.
Work is expected to continue for the next two-and-a-half weeks through Wednesday, Nov. 3.
A list of the areas that will be affected by this year’s program can be found below.
Town officials say the schedule could change depending on the condition of mains, weather, traffic control, manpower, and equipment issues.
Day 1
- Isaac Street to Kaitlyn Street, Paige Street to Kaitlyn Street, trunk main to Dobson Lane, Backflush under railway towards Monaco Drive
- Carriage Way and Longwood Drive, Aspen Drive.
Day 2
- Capri Avenue, Seville Row, Aries Court, Monaco Drive (civic # 56 – 46), Holland Drive
- Bel-Air Ave, Phoenix Court
Day 3
- 66 Bel-Air Ave to intersection at Monaco Drive and Oakville Lane
- Previous manhole to 44 Monaco Drive
- Previous manhole back flush towards Dobbin Street.
- Sierra Avenue
Day 4
- Cortland Place, Dobbin Street, branch from Lennox Drive and thru to Master Drive
- Scott Avenue, Spruce Street
Day 5
- Sprucewood Avenue, Hibbard Lane, Almond Lane,
Day 6
- Gondola Point Road (civic # 58 – 38, 63 – 76, 88 – 76, 87 – 122) (Flaggers)
- Hampton Road (civic # 100 – 154) (Flaggers)
Day 7
- Hampton Road (civic # 10 – 1), 3180 Rothesay Road to Rothesay Corner (Flaggers)
Day 8
- Station Road trunk main
Day 9
- Maiden Lane, Knoll Lane, Goldie Court
- Tennis Court Road trunk main along tracks to Tennis Court Lift Station.
Day 10
- Alexander Avenue, Rothesay Park Road
- Higginson Avenue, Horton Road
- Dunedin Road, Newport Drive
Day 11
- Appleby Drive
- Rothesay Road civic # 2392 to 10 Appleby Drive, 2316 Rothesay Road to 10 Appleby Drive (Flaggers)
- Taylor Brook bridge to bottom of College Hill Road (Flaggers)
- High Cliff Court, Riverside Drive and Burnett Terrace
Day 12
- Millwood Lane
- Riverside Lift Station grit chamber
- K-park Lift Station
- Fairvale Lift Station